Find street closures and other traffic advisories anywhere in Oklahoma City using an interactive map on the Public Works website.
Find and sign up for updates about OKC Streetcar-related construction on the MAPS 3 website.
Each project’s duration is subject to the weather and other factors.
City of Oklahoma City projects
Media Contact: Shannon Cox, (405) 297-2130, shannon.cox@okc.gov
E.K. Gaylord Boulevard (between Reno and Sheridan avenues)
- E.K. Gaylord narrowed.
- Expected completion: End of summer.
- Part of Project 180.
OKC Streetcar projects
Media Contact: Kristen Torkelson, (405) 239-3297, ktorkelson@adgokc.com
Joe Carter Avenue (between Sheridan and Reno avenues)
- One lane of traffic in each direction will be open on the east side of the street.
- Expected completion: July 7.
Reno Avenue (between Joe Carter Avenue and Oklahoma Avenue)
- The northernmost westbound lane will be closed for concrete work and foundation work.
- Expected completion: July 3.
Sheridan Avenue (between E.K. Gaylord Boulevard and Joe Carter Avenue)
- One lane of traffic will be open in each direction on the north side of the street as road demolition continues.
- Expected completion: July 7.
Sheridan Avenue and Mickey Mantle Drive
- The intersection will be closed for road demolition. It will be open in the evenings and not closed at the same time as Oklahoma Avenue.
- Expected completion: June 30.
NW 10th Street (between Walker and Hudson avenues)
- NW 10th Street is closed between Walker and Hudson for utility work.
- Expected completion: June 9.
Hudson Avenue (at Sheridan Avenue)
- Traffic on both streets will be narrowed while storm and sanitary work continues.
- Expected completion: May 31.
Hudson Avenue (between SW 2nd and SW 3rd streets)
- Hudson will be closed to conduct sanitary sewer work.
- Expected completion: May 26.
Hudson Avenue (between SW 3rd and SW 7th streets)
- Hudson will be closed for road demolition and track installation.
- Expected completion: June 30.
Harvey Avenue (north of SW 3rd Street)
- Harvey will be closed in both directions for half a block north of SW 3rd for road demolition.
- The road can be re-opened nightly if needed during the track construction phase.
- Expected completion: May 26.
Robinson Avenue (between Reno Avenue and SW 3rd Street)
- Robinson will be narrowed to one lane in each direction for utility work.
- Expected completion: June 9.
Private Projects
W Sheridan Avenue (between Classen Boulevard and Shartel Avenue)
- Closed to traffic.
- Scheduled to open by May 23.
W Sheridan Avenue (between Hudson and Walker avenues)
- Narrowed in both directions.
- Expected completion: End of summer.
- Contractor: J.E. Dunn.
###